SPMB: Supply and transportation of Primary Equipment and Materials

0:00 / 0:00
0:00
Southern Vietnam Power Projects Management Board (SPMB) issued on December 17, 2021 its notice of its notice of bid invitation for procurement package of Processing 1000 sq. km AVA/AVO inversion within Block 16-1/15 with details as follows:

Procuring agency: Southern Vietnam Power Projects Management Board (SPMB)

Name of procurement package: Package 7: Supply and transportation of Primary Equipment and Materials “Notice ref No 20211256959 - 00. Date of publication: 17/12/2021 09:34"

- Implementation period: 180 days

Project name: Upgrading power of 500kV Dak Nong substation

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 09:34 am, 17 December 2021 to 09:00 am, 27 January 2022 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000 or USD 200

Bid security: VND 1,086,000,000 or USD 47,684 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 27 January 2022

Bid opening time: 09:15 am, 27 January 2022

Chuyên đề