Procuring agency: Southern Vietnam Power Projects Management Board (SPMB)
Name of procurement package: Package 7: Supply and transportation of Primary Equipment and Materials “Notice ref No 20211256959 - 00. Date of publication: 17/12/2021 09:34"
- Implementation period: 180 days
Project name: Upgrading power of 500kV Dak Nong substation
Source of fund: EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 09:34 am, 17 December 2021 to 09:00 am, 27 January 2022 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 4,700,000 or USD 200
Bid security: VND 1,086,000,000 or USD 47,684 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 27 January 2022