Southern Vietnam Power Projects Management Board (SPMB) issued on March 18, 2021 its notice of its notice of bid invitation for procurement package of Supply and transportation of Insulator and fittings, OPGW and fittings with details as follows:

Procuring agency: Southern Vietnam Power Projects Management Board (SPMB)

Name of procurement package: Package No.10: Supply and transportation of Insulator and fittings, OPGW and fittings “Notice ref No 20210342866 - 00. Date of publication: 18/03/2021 15:53"

- Implementation period: 180 days

Project name: Build 500kV Duc Hoa – Chon Thanh Transmission Line

Source of fund: EVN NPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 03:53 pm, 18 March 2021 to 09:00 am, 28 April 2021 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000

Bid security: VND 1,885,000,000 or USD 81,510 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 28 April 2021

Bid opening time: 09:15 am, 28 April 2021.