Procuring agency: Southern Vietnam Power Projects Management Board (SPMB)
Name of procurement package: Package 6: Supply and transportation of Primary Equipment and Materials (Notice ref No.: 20220633782 - 00. Date of publication: 11/06/2022 16:29)
- Implementation period: 240 days
Project name: Upgrading power of 500kV Song May substation
Source of fund: EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 04:29 pm, 11 June 2022 to 09:00 am, 22 July 2022 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 4,700,000 or USD 200
Bid security: VND 1,130,000,000 or USD 48,640 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 22 July 2022
Bid opening time: 09:15 am, 22 July 2022.