Procuring agency: Department of Planning and Investment of Quang Binh province

Project name: Bao Ninh 4 urban center, Bao Ninh commune, Dong Hoi city (new urban center) “Notice ref No PR2300012114 - 00. Date of publication: 28/03/2023 17:13"

Investment objectives: Actualizing the detailed construction master plan with ratio 1/500, housing development plan and program; land use master plan approved by competent authorities; establishing the new urban center to meet the demand of housing, to serve the livelihood of people within the region; supplying facilities for residential community; creating landscape architecture of the region; gradually embellishing and upgrading urban areas; mobilizing the out-of-state’s budget capital from investors, enterprises to implement the task of ground clearance, and invest in socio-economic infrastructure; promoting the local socio-economic development

Project scale: 1) Land use area: About 415.224 m2 2) Construction scale: a) Part of technical infrastructure works: invest in complete construction of technical infrastructure with the land use area of about 415.224 m2 ; b) Part of housing works: - Commercial housings: + Terraced houses: construct at least about 147 terraced houses + Apartment building: constructing 04 apartment buildings; - Social housings: Invest in constructing 02 apartment buildings of social housings c) Part of social infrastructure works: - Construct 01 nursery school (Details are attached with the decision to approve the investment policy).

Project implementation progress: Operational time: within 50 years since the date investors having land granted, land leased; buyers of housing attached with residential land use right or buyers of residential land for housing construction will have the stable and long term use right. - Project implementation progress: Not over 8 years since the date having the investor selection approval decision or investor approval decision, expected from the year 2022 to the year 2030

Project location: Bao Ninh commune, Dong Hoi City, Quang Binh province

Land area: About 415.224 m2

Land use period: -

Land use's purpose: New residential land; water surface; traffic land; parking lot; technical infrastructure land (R3); nursery school land; green tree landscape land; public land, land for sports and cultural works

Current status of the land area: Production forest land (RSX); non-agricultural production land (SKC); flat land for cultivation of annual crops (BHK); Traffic land (DGT)

Preliminary total project implementation cost: VND 2.458.645.000.000

Compensation, support and resettlement expense: VND 12.569.000.000

Deadline for investors to submit their project implementation registration document:18/05/2023 10:43

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Quang Binh province, 23/8 road, Dong Phu ward, Dong Hoi city, Quang Binh province. Phone number: 02323822270.

Chuyên đề