Southern Vietnam Power Projects Management Board (SPMB) published Invitation to bid on Vietnam Public Procurement Review issue No. 38 dated 02 March 2020 with the following contents:
 

Procurement package Package No.09: Supply of Insulator & Fittings, OPGW & Fittings for Transmission Lines “Notice ref No.: 20200261521 - 00. Date of publication: 28/02/2020 09:06".

Project name: Build 500kV Long Thanh – Bifurcate Phu My – Song May Transmission Lines

Time of issuing bidding documents: from 09:06 am, 28 February 2020 to 09:00 am, 09 April 2020 (during office hours)

Bid opening time: 09:15 am, 09 April 2020

Now we would like extend:

Time of issuing bidding documents: before 09:00 am, 16 April 2020 (during office hours)

Bid opening time: 09:15 am, 16 April 2020.

Other information remains unchanged.