Package 8: Supply and transportation of insulator & fittings, opgw & fittings for connection line

Procuring agency: Southern Vietnam Power Projects Management Board – Branch of National Power Transmission Corporation

Name of procurement: Package 8: Supply and transportation of insulator & fittings, opgw & fittings for connection line (Notice ref No IB2300050306 - 00. Date of publication: 27/03/2023 10:36)

- Implementation period: 240 days

Project name: 220KV Dinh Quan Substation and Connection Lines

Source of fund: National Power Transmission Corporation

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 10:36 am, 27 March 2023 to 09:00 am, 08 May 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000

Bid security: VND 1.226.911.000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 08 May 2023

Bid opening time: 09:15 am, 08 May 2023.