Procuring agency: Southern Vietnam Power Projects Management Board (SPMB)
Name of procurement package: Package 6: Supply and installation of Dissolved Gas Analysis (DGA) - Gas-in-oil online monitoring system for 500kV transformers “Notice ref No.: 20200202993 - 00. Date of publication: 05/02/2020 08:17".
- Implementation period: 150 days
Project name: Power enhancement for 500kV Di Linh Substation from 450MVA to 900MVA
Source of fund: EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 08:17 am, 05 February 2020 to 09:00 am, 19 March 2020 (during office hours)
Place of issuing bidding documents: Southern Vietnam Power Projects Management Board (SPMB) No. 610 Vo Van Kiet Street, Cau Kho Ward, District 1, Ho Chi Minh City, Vietnam. Tel : (84-28) 2210 0719; Fax : (84-28) 3836 1096
Price of bidding documents: VND 4,600,000 or USD 200
Bid security: VND 230,000,000 or USD 9,916 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 19 March 2020
Bid opening time: 09:15 am, 19 March 2020.