Procuring agency: Department of Planning and Investment of Quang Ninh province

Project name: Port 1 in the Mong Duong - Khe Day port cluster in Mong Duong Ward, Cam Pha City “Notice ref No PR2300018023 - 00. Date of publication: 28/04/2023 16:57"

Investment objectives: To invest in the construction of a comprehensive and modern port cluster, bringing the Mong Duong - Khe Day port cluster in line with the unified planning. Upgrading the transportation network, contributing to the improvement of local infrastructure, promoting economic development along with enhancing the protection of security and social order for the area. Establishing a hub for material transshipment from the source of waste rock to serve landfill projects both within and outside the budget, providing for neighboring areas within the province from Cam Pha City. Ensuring a sustainable environment for port development.

Project scale: The total land and water area for implementing the project is 378,852.8 m2, including: The land area for the project is 330,679.1 m2; The area of water in front of the wharf (located within the boundary of the lowest average sea level for many years) is 18,538.75 m2; The area of water in front of the wharf (located outside the boundary of the lowest average sea level for many years) is 24,715.05 m2; The area of transportation, technical infrastructure outside the project fence is 4,919.9 m2 Investment on construction of a port terminal on a total land area of 13,286.3 square meters. This area will include a single-story warehouse complex with a building area of 2,400 square meters, a construction density of 18.1%, and a floor area of 2,400 square meters. Additionally, there will be a port area of 9,835.2 square meters and technical infrastructure (coastal embankment) of 1,051.1 square meters. Investment on construction of an executive office building on the land plot marked as "DH," which will include a two-story executive building, a staff dormitory, a connecting bridge, a guardhouse, and a parking lot. The total land area is approximately 15,533 square meters, with a construction density of 15.7%, a building area of around 2,442.5 square meters, and a height of 1-2 floors. The total floor area is approximately 3,908.5 square meters. Investment on construction of two auxiliary buildings on the land plot marked as "PT," with a total land area of 7,134.5 square meters, a height of one floor, a construction density of 33.6%, a building area of 2,400 square meters, and a floor area of 2,400 square meters. Investment on completing the internal technical infrastructure with an area of 267,293.7 square meters. For the technical infrastructure outside the project boundary with an area of 4,919.9 square meters: The investor will be selected to invest in comprehensive technical infrastructure within the project area according to the approved detailed construction plan

Project implementation progress: Project implementation schedule: - Complete investment preparation and commence investment construction: From 2nd Quarter 2023 to 4th Quarter 2025. - Complete investment construction and put the entire project into operation: In 1st Quarter 2026

Project location: Mong Duong Ward, Cam Pha City, Quang Ninh province

Land area: -

Land use period: -

Land use's purpose: Investment in constructing a general cargo port (transportation land)

Current status of the land area: The total area of land and water surface for the project implementation is 378,852.8 square meters, including: A portion of approximately 324,000 square meters managed and used by two households for the purpose of forest planting and aquaculture, with current status of planted trees, ponds, and temporary structures. The remaining area is public land and water surface managed by the People's Committee of Mong Duong Ward, with a status of concrete road, vacant land, and unused water surface. - Current land use structure: Flat land near the mountain: 53,157.9 m2 (14%); Water surface Area: 178,558.7 m2 (47.1%); Hill land: 58,380.1 m2 (15.4%); Sloping land: 42,941.2 m2 (11.3%); Land for transportation and other technical infrastructure: 45,814.9 m2 (12.2%). - Land reclamation conditions: Implement land reclamation in accordance with Clause 2, Article 62 of the Land Law No. 45/2013/QH13 dated November 29, 2013. The project has been approved in Resolution No. 106/NQ-HDND dated July 9, 2022

Preliminary total project implementation cost: VND 779.514.000.000

Compensation, support and resettlement expense: VND 58.500.000.000

Deadline for investors to submit their project implementation registration document: 16/06/2023 16:30

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Quang Ninh province, Hong Ha ward, Ha Long City, Quang Ninh province. Phone number: 0203.3835687