Procuring agency: Central Power Projects Management Board (CPMB)

Name of procurement: The package No.12: Supply and transportation primary equipment & materials, insulators, OPGW and accessories (Notice ref No.: IB2300008395 - 00. Date of publication: 16/01/2023 10:46)

- Implementation period: 210 days

Project name: 220kV Tuong Duong-Do Luong transmission line

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 10:46 am, 16 January 2023 to 09:00 am, 07 March 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,800,000

Bid security: VND 1,080,000,000 or USD 45,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 07 March 2023

Bid opening time: 09:00 am, 07 March 2023.