EVNNPT-NPMB: Supply and Delivery of Primary Equipment and Materials for Substation and Extension

0:00 / 0:00
0:00
The Northern Vietnam Power Projects Management Board-Branch of the National Power Transmission Corporation (EVNNPT-NPMB) issued on September 14, 2021 its notice of its notice of bid invitation for procurement package of Supply and Delivery of Primary Equipment and Materials for Substation and Extension with details as follows:

Procuring agency: The Northern Vietnam Power Projects Management Board-Branch of the National Power Transmission Corporation (EVNNPT-NPMB)

Name of procurement package: Package 08: Supply and Delivery of Primary Equipment and Materials for Substation and Extension “Notice ref No 20210930741 - 00. Date of publication: 14/09/2021 14:24"

- Implementation period: 180 days

Project name: 220kV Ba Thien substation and 220kV Viet Tri – Tam Duong – Ba Thien transmission line

Source of fund: The National Power Transmission Corporation (EVNNPT)

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 02:24 pm, 14 September 2021 to 02:00 pm, 25 October 2021 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,500,000

Bid security: VND 1,117,000,000 or USD 48,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 02:00 pm, 25 October 2021

Bid opening time: 02:30 pm, 25 October 2021.

Chuyên đề