Procuring agency: Department of Planning and Investment of Quang Ninh Province
Project name: Quang Ninh LNG gas power plant project “Notice ref No 20210693589 - 00. Date of publication: 29/06/2020 16:48"
Project's investment objectives: Electricity Trading. Contributing to ensuring the capacity compensation for the national electrical system in the coming years. Enhancing the power supply reliability, reducing loss due to long-distance transmission, improving the power quality; contributing to sharing the financial burden for the electricity industry in investment and development of power sources. Meeting environmental standards, contributing to the reduction of greenhouse gas emissions; promoting industries, transportations, and services, and creating more local business opportunities
Scale of the project investment: a) Gas Power Plant: (1) 01 gas power plant using combined cycle gas turbine technology, capacity 1,500 MW; (2) a 500 kV distribution yard ensuring the transmission of the power plant's 1,500 MW capacity; (3) Construction of infrastructure and technical works for power plants, including a cooling water channel, a canal carries the discharge water, a canal carries domestic wastewater, internal roads, and connections with local transport infrastructure. b) LNG ports and depots: (1) an LNG import terminal meeting the scale output through the port of 2.4 million tons of LNG/year: 01 docking station and ancillary items; LNG transport pipeline from the LNG import terminal to the depots meeting the scale output through the port of 2.4 million tons of LNG/year; LNG depots with the capacity of 1.4 million tons per year, with 2 on-land tanks, each tank has a capacity of 100,000 m3; (2) Regasification area for Gas Power Plants with a capacity of 1,500MW. (3) Equipment and ancillary items
Preliminary total project implementation cost: VND 47.350.000.000.000
Compensation, support and resettlement expense: VND 130.000.000.000
Summary of the basic requirements of the project: Investing in the construction of Quang Ninh LNG gas power plant in Cam Thinh ward, Cam Pha city, ensuring synchronization according to the approved objectives, scale, and planning
Investment duration and schedule: Project operation term: 50 years (from the date the Investor is allocated or leased land). Investment progress: Completing investment preparation: In the first quarter of 2022. + Deploying investment and construction of the project: from the second quarter of 2022 - the second quarter of 2027. Completing and putting the project into operation: In the third quarter of 2027
Project location: Cam Thinh ward, Cam Pha city, Quang Ninh province
Land area: Total area 55.89 ha, including 42.51 ha of land and 13.38 ha of water surface (excluding the water area in front of the wharf, channel, and turning area)
Land use's purpose: Industrial land used to build Quang Ninh gas power plant
Approved planning criteria: Land for construction of power plants and LNG depots: 42.51 ha in which: Area for depots and regasification is 9.74 ha; power plant construction area is 32.77 ha. - The water surface area is 13.38 ha, of which: The area for gas supply and cooling water discharge is 9.56 ha; the LNG port area is 1.45 ha; the area for cooling water supply pipeline is 2.37 ha
Deadline for investors to submit their project implementation registration document: 29/07/2021 16:37
Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Quang Ninh Province, 5th floor, Inter-agency headquarters No. 2, Hong Ha ward, Ha Long city, Quang Ninh province. Phone number: 0203.3835687; Fax number: 0203.3838071; Email: skhvdt@quangninh.gov.vn
Other information: According to Decision No. 1976/QD-UBND dated June 23, 2021, of the People's Committee of Quang Ninh province "On approving category of the land-use project which need investor selection for Quang Ninh LNG Gas Power plant Project”.