Procuring agency: Central Power Projects Management Board (CPMB)
Name of procurement package: Package No. 07: Supply and transportation of primary equipment and accessories “Notice ref No.: 20200104806 - 00. Date of publication: 03/01/2020 13:29".
- Implementation period: 180 days
Project name: 220kV Lao Bao substation and 220kV Dong Ha – Lao Bao
Source of fund: EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 08:00 am, 09 January 2020 to 09:00 am, 27 February 2020 (during office hours)
Place of issuing bidding documents: Central Power Projects Management Board (CPMB), 478 September 2nd Road, Da Nang City, Vietnam. Tel: 84-0236-222 1579; Fax: 84-0236-222 0367
Price of bidding documents: VND 4,700,000 or USD 200
Bid security: VND 930,000,000 or USD 40,000 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 27 February 2020
Bid opening time: 09:00 am, 27 February 2020.