The Northern Vietnam Power Projects Management Board: Package NQPLTT-G06

The Northern Vietnam Power Projects Management Board would like to notify the bidding result of Package NQPLTT-G06: Supply and Delivery of Conductors and Earthwires from Nho Quan (ĐĐ) - G4A, G33- 500kV Thuong Tin Substation (ĐC2) and Move 110kV Transmission Line for 500/220kV Nho Quan-Phu Ly-Thuong Tin Transmission Line, detail as below:

The Northern Vietnam Power Projects Management Board: Package NQPLTT-G07

The Northern Vietnam Power Projects Management Board would like to notify the bidding result of Package NQPLTT-G07: Supply and Delivery of Conductors and Earthwires from G4A - G33 - 220kV Phu Ly Substation (ĐC1) for 500/220kV Nho Quan-Phu Ly-Thuong Tin Transmission Line, detail as below: