- Implementation period: 180 days
Project name: Block 09-1
Source of fund: Vietsovpetro’s financial plan for production activities in the year 2022 for Block 09-1.
Method of bidder selection: International open bidding, one-stage one envelope bidding
Time of issuing bidding documents: from 02:54 pm, 25 May 2023 to 09:00 am, 07 July 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 500,000
Bid security: VND 65,000,000 or USD 2,700 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 07 July 2023
Bid opening time: 09:30 am, 07 July 2023.