Procuring agency: Vietsovpetro Joint Venture

0:00 / 0:00
0:00
Name of procurement package Material for dismantling section of subsea pipeline 26" and SSIV at BK4A (Package No.VT-699/22-XL-DA) (Notice ref No.: IB2200106436 - 00. Date of publication: 30/12/2022 08:02)

- Implementation period: 70 days

Project name: Block 09.1

Source of fund: The source of funding for implementation of the bidding package is Vietsovpetro’s financial plan for production activities in 2022-2023

Method of bidder selection: International open bidding, one-stage one envelope bidding

Time of issuing bidding documents: from 08:02 am, 30 December 2022 to 09:00 am, 08 February 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 500,000

Bid security: VND 17,200,000 or USD 700 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 08 February 2023

Bid opening time: 09:15 am, 08 February 2023.