- Implementation period: 330 days
Project name: Son My LNG Terminal
Source of fund: Owner Capital (Capital for research and investment preparation of the Project).
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 06:51 pm, 25 May 2023 to 10:00 am, 07 July 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 5,500,000
Bid closing time: 10:00 am, 07 July 2023
Bid opening time: 10:30 am, 07 July 2023.