Procuring agency: Department of Planning and Investment of Soc Trang province

Project name: Worker housing in the service area and worker dormitory in An Nghiep Industrial Park, Ward 7, Soc Trang city, Soc Trang province “Notice ref No PR2300027549 - 00. Date of publication: 21/06/2023 11:21"

Investment objectives: Create the best living space conditions, meet the accommodation needs and improve the quality of life for employees working at enterprises in the industrial park with complete construction of traffic system, technical and social infrastructure.

Project scale: 1. Total project area: About 11.405 ha. 2. Population: About 4,165 people. 3. Preliminary structure of housing products - Build 07 social housing buildings in the form of apartments with about 1,030 apartments; construction land area is about 39,374 m2; the maximum construction floor area is about 131,960 m2; the maximum number of floors is 05 floors; the maximum building density is 75%. - Build adjacent social housing blocks with about 101 apartments; construction land area is about 6,944 m2; the maximum construction floor area is about 12,540 m2; the maximum number of floors is 02 floors; the maximum building density is 100%. 4. Estimated structure of land use No. Land type Area (m²) Rate (%) Notes 1 Residential land 46,318 40.61 1.1 Apartment residential land 39,374 1.2 Adjacent residential land 6,944 2 Land for education 7,011 6.15 3 Land for green trees - Sports 15,714 13.78 4 Land for technical infrastructure works 4,553 3.99 4.1 Technical alley 3,486 4.2 Wastewater treatment station 1,067 5 Land for traffic 40,454 35.47 The province supports the construction of this part from the local budget Total 114,050 100.00 5. Specific scale: Comply with the construction planning of corresponding items in the detailed planning of 1/500 scale project of Service area and worker dormitory in An Nghiep Industrial Park, Soc Trang province approved by competent authorities approval authority. 6. Preliminary plan for investment in construction and infrastructure management within the scope of the Project: The investor shall invest in construction, management, operation, exploitation and repair and maintenance in order to maintain the operation of the project of the wastewater treatment station within the scope of the Project during the operation of the Project; at the same time, handing over to the State according to the provisions of current law.

Project implementation progress: 1. Term of operation of the project: 50 years from the date of issuance of the decision on land allocation by a competent state agency. 2. Investment progress 2.1. Capital contribution and capital mobilization progress: Capital contribution and capital mobilization follow the project implementation schedule. 2.2. Project implementation schedule: maximum 04 years (48 months). - Time to start the project: No more than 06 months from the date of the decision on land allocation issued by the competent state agency. - Time to carry out construction and complete, put into operation and exploit the whole project: No more than 48 months from the date of issuance of land allocation decision of competent state agency.

Project location: 7 ward, Soc Trang City, Soc Trang province

Land area: About 11.405 ha

Land use period: -

Land use's purpose: To build a social housing project according to the approved detailed planning

Current status of the land area: Land is being cleared.

Preliminary total project implementation cost: VND 947.909.000.000

Compensation, support and resettlement expense: VND 50.084.933.032

Deadline for investors to submit their project implementation registration document: 21/07/2023 15:00

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Soc Trang province, No 11 Tran Hung Dao road, 3 ward, Soc Trang City, Soc Trang province. Phone number: 02993822333

Chuyên đề