Procurement package: Package No.10: Supply and transportation of Insulator and fittings, OPGW and fittings “Notice ref No 20210342866 - 00. Date of publication: 18/03/2021 15:53"
Project name: Build 500kV Duc Hoa – Chon Thanh Transmission Line
Time of issuing bidding documents: from 03:53 pm, 18 March 2021 to 09:00 am, 28 April 2021 (during office hours)
Bid opening time: 09:15 am, 28 April 2021.
Now we would like to change:
Time of issuing bidding documents: before 09:00 am, 12 May 2021 (during office hours)
Bid opening time: 09:15 am, 12 May 2021
Other information remains unchanged.