(Notice of bid extension) EVNNPT-NPMB: Supply and Delivery of 500/220/35kV Auto-transformer

0:00 / 0:00
0:00
The Northern Vietnam Power Projects Management Board-Branch of the National Power Transmission Corporation (EVNNPT-NPMB) published Invitation to bid on Vietnam Public Procurement Review issue No.116 dated 24 June 2022 with the following contents:

Procurement package: Package 05: Supply and Delivery of 500/220/35kV Auto-transformer (Notice ref No.: 20220532670 - 00. Date of publication: 13/05/2022 16:49)

Project name: Vinh Yen 5000kV Substation and Connection

Time of issuing bidding documents: from 04:49 pm, 13 May 2022 to 09:00 am, 01 July 2022 (during office hours)

Bid opening time: 09:30 am, 01 July 2022.

Now we would like to change:

Time of issuing bidding documents: before 09:00 am, 07 July 2022 (during office hours)

Bid opening time: 09:30 am, 07 July 2022

Other information remains unchanged.