Binh Dinh Department of Construction: Long Van Social Housing

0:00 / 0:00
0:00
Binh Dinh Department of Construction issued on August 20, 2021 its notice of its notice of bid invitation for project of Long Van Social Housing with details as follows:

Procuring agency: Binh Dinh Department of Construction

Project name: Long Van Social Housing “Notice ref No 20210842122 - 00. Date of publication: 20/08/2021 12:32"

Project's investment objectives: To settle the demand on social housing for subjects regulated at Article 49 of Housing Law in 2014. - To contribute to completing the plan for social housing development in Binh Dinh Province, period of 2016-2020 and supplement the period of 2021-2025 issued under Decision No 33/2019/QD-UBND dated 19/7/2019. - To specify the detailed planning project for construction with scale of 1/500 under the Social Housing Area of Long Van Urban Zone, Tran Quang Dieu Ward, Quy Nhon City ratified by Chairman of People’s Committee of Binh Dinh Province under Decision No 1032/QD-UBND dated 25/3/2020 and Decision No 2138/QD-UBND dated 27/5/2021 by Provincial People’s Committee approved the adjustment of Decision No 1032/QD-UBND dated 25/3/2020 by Provincial People’s Committee. - To contribute to the refurbishment, enhancement of environmental quality and urban landscape architecture

Scale of the project investment: The investment in new construction of Long Van Social Housing under Long Van Urban Zone, Tran Quang Dieu Ward, Quy Nhon City is under the form of apartment with scale of 21 floors ( including the attic and technical floor), about 828 flats. The construction for completion of technical infrastructure system is within the project

Preliminary total project implementation cost: VND 860.148.406.000

Compensation, support and resettlement expense: -

Summary of the basic requirements of the project: The implementation for project investment was under the planning that was approved by competent state agencies; ensuring the proposed schedule

Investment duration and schedule: Time limit for project activities: 50 years - Investment schedule: in 2021-2024

Project location: Long Van Urban Zone, Tran Quang Dieu Ward, Quy Nhon City

Land area: About 20.347m2

Land use's purpose: For the residential land: the state has allocated the land under regulations of law on land; home buyers affixing to the land use right used stably and long. For the infrastructure land: the state has handovered the land to investors under detailed planning that was approved by competent agency. After the construction was completed, the investors have handovered a part of works to the Board for apartment management and a part of works to the locality (if any) for management

Approved planning criteria: According to the Decision No 1032/QD-UBND dated 25/3/2020 and the Decision No 2138/QD-UBND dated 27/5/2021 by Provincial People’s Committee approved the adjustment of Decision No 1032/QD-UBND dated 25/3/2020 by Provincial People’s Committee

Deadline for investors to submit their project implementation registration document: 24/09/2021 08:00

Address, phone number, fax number of the Department of Planning and Investment: Contacting the Board for investment project management under the form of public and private partner (PPP) and the investment project with land use to receive the guidances and relevant documents, please. Address: 32 Ly Thuong Kiet, Ly Thuong Kiet Ward, Quy Nhon City, Binh Dinh Province. Tel: 02563 822 882

Other information: The status quo of land was the ground that has not been cleared yet, including the rice field land, unused flat land

Chuyên đề