Procuring agency: Power Transmission Project Management Board (NPTPMB) - Branch of National Power Transmission Corporation (EVNNPT)

Name of procurement: Package No. 5B: Supply and transportation of primary equipment and materials (Notice ref IB2300230538 - 00. Date of publication: 14/09/2023 08:36)

- Implementation period: 180 days

Project name: Installation of Auto-transformer no.3 at 220kV Nha Be Substation and Installation of Auto-transformer no.2 at 220kV Thai Thuy Substation

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 08:36 am, 14 September 2023 to 10:00 am, 24 October 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: Free of charge

Bid security: VND 906,516,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 10:00 am, 24 October 2023

Bid opening time: 10:00 am, 24 October 2023.