NPTPMB: Package No. 5 Supply and transportation of 220kV current limiting reactor and materials, equipment, including

0:00 / 0:00
0:00
Procuring agency: Power Transmission Project Management Board (NPTPMB) - Branch of National Power Transmission Corporation (EVNNPT)

Name of procurement package: Package No. 5 Supply and transportation of 220kV current limiting reactor and materials, equipment, including (Notice ref No.: 20220564906 - 00. Date of publication: 24/05/2022 17:29)

- Lot 5.1: 500kV Hiep Hoa substation.

- Lot 5.2: 220kV Trang Bach substation for the above mentioned

- Implementation period: 240 days

Project name: Installation of short-circuit current limiting equipment

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 05:29 pm, 24 May 2022 to 09:00 am, 07 July 2022 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,600,000 or USD 200

Bid security: VND 2,008,000,000 through banks or branches which legally operate in Viet Nam

+ Lot 5.1: VND 990,000,000 or 43,000

+ Lot 5.2: VND 1,018,000,000 or 44,000

Bid closing time: 09:00 am, 07 July 2022

Bid opening time: 09:15 am, 07 July 2022.