- Implementation period: 120 days
Project name: MSP6
Source of fund: The source of funding for implementation of the bidding package is Vietsovpetro’s financial plan for production activities in 2023
Method of bidder selection: International open bidding, one-stage one envelope bidding
Time of issuing bidding documents: from 08:59 am, 15 March 2023 to 02:00 pm, 25 April 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 500,000
Bid security: VND 49,200,000 or USD 2,110 through banks or branches which legally operate in Viet Nam
Bid closing time: 02:00 pm, 25 April 2023
Bid opening time: 02:30 pm, 25 April 2023