Procuring agency: Southern Power Projects Management Board (SPMB) – Branch of National Power Transmission Corporation (EVNNPT)

Name of procurement: Package 14: Supply and transportation of primary equipment and materials (Notice ref No.: IB2300034336 - 00. Date of publication: 07/03/2023 15:27)

- Implementation period: 240 days

Project name: 220kV Vinh Chau substation and transmission lines.

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 03:27 pm, 07 March 2023 to 09:00 am, 17 April 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000

Bid security: VND 790,000,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 17 April 2023

Bid opening time: 09:15 am, 17 April 2023.