Procuring agency: Department of Planning and Investment of Hai Phong City

Project name: Construction project of Hoang Xa new urban area, An Lao town, An Lao district “Notice ref No PR2300006722 - 00. Date of publication: 22/02/2023 10:15"

Investment objectives: Investing in the construction of Hoang Xa new urban area project, An Lao town, An Lao district with synchronous technical infrastructure, full facilities, contributing to promoting socio-economic development of An Lao district in particular and Hai Phong city in general, meeting housing needs and improving the quality of life of local people. The project will create a modern civilized urban space, renovate the landscape of An Lao district, Hai Phong city

Project scale: Leveling, building synchronous technical infrastructure throughout the land. Build 900 semi-detached houses, 3-5 floors high, area from 80-120m2 and 62 villas, 3-storey high, area from 180-250m2. Total construction floor area is about 291,939m2; + Construction of cultural houses: Construction area of 800 m2; + Construction of car park: Construction area of 5,510 m2; + Construction of trade and service centers, hotels: Construction area 11,082.16m2, 17 floors high (02 basements and 15 floating floors); - The project spends a land fund of 26,388.26m2 for social housing development, this land fund is handed over to the locality by the investor after having invested in technical infrastructure

Project implementation progress: Project implementation period: 50 years from the date of land allocation by the City People's Committee. - Project implementation schedule: + Progress of capital contribution and mobilization of capital sources: According to the construction progress of works under the Project. + Progress of basic construction and putting the work into operation: 60 months from the effective date of the project contract, of which: The estimated time for site clearance is 06 months; The project construction investment period is 54 months from the time of being allocated or leased land by a competent state agency for project implementation

Project location: An Lao town, An Lao District, Hai Phong City

Land area: 34.86 ha

Land use's purpose: Residential land, green land, public land and traffic land

Current status of the land area: agricultural land, in-field traffic land, in-field irrigation land

Preliminary total project implementation cost: VND 3.262.320.000.000

Compensation, support and resettlement expense: VND 175.794.203.000

Deadline for investors to submit their project implementation registration document: 25/03/2023 09:00

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Hai Phong City, 01 Dinh Tien Hoang road, Minh Khai ward, Hong Bang District, Hai Phong City. Phone number: 02253842614.

Chuyên đề