Central Power Projects Management Board: Supply and transportation of primary equipment & materials, conductor, insulator, OPGW and accessories

Central Power Projects Management Board issued on August 26, 2020 its notice of its notice of bid invitation for procurement package of Supply and transportation of primary equipment & materials, conductor, insulator, OPGW and accessories with details as follows:

Procuring agency: Central Power Projects Management Board (CPMB)

Name of procurement package: Package No. 07: Supply and transportation of primary equipment & materials, conductor, insulator, OPGW and accessories “Notice ref No 20200876820 - 00. Date of publication: 26/08/2020 14:43"

- Implementation period: 180 days

Project name: 220kV Duy Xuyen substation

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 02:43 pm, 25 August 2020 to 09:00 am, 12 September 2020 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000 or USD 200

Bid security: VND 1,160,000,000 or USD 50,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 12 September 2020

Bid opening time: 09:00 am, 12 September 2020.