Procuring agency: Vietnam Electricity Power Projects Management Board No. 1 - Vietnam Electricity Branch (EVNPMB1)
Name of procurement package: Package No. 1TB-HB "Supply of Electro-Mechanical Equipment” “Notice ref No 20210228651 - 00. Date of publication: 22/02/2021 15:01"
- Implementation period: 40 months
Project name: Hoa Binh Hydropower Plant Extension Project
Source of fund: Equity of EVN, Commercial Loans
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 03:01 pm, 22 February 2021 to 09:30 am, 22 April 2021 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 7,000,000
Bid security: VND 46,000,000,000 or USD 2,000,000 or EUR 1,650,000 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:30 am, 22 April 2021
Bid opening time: 10:00 am, 22 April 2021.