Procurement package: Package Nº: CPC-KFW3.2-G02 Package Title: Supply and transport primary and secondary equipment, computerised control system, communication system for 110kV Substations: Tay Bac Quan Hau, Cam Lo, Vinh Thanh, KCN Phu Bai 2, Gia Nghia, Hoa Phong “Notice ref No 20200975107 - 00. Date of publication: 28/09/2020 13:52"

Project name: Project Efficient Power Grids in Small and Medium-Sized Cities – Phase 2

Time of issuing bidding documents: from 01:52 am, 28 September 2020 to 09:00 am, 16 November 2020 (during office hours)

Bid opening time: 09:00 am, 16 November 2020.

Now we would like to extend:

Time of issuing bidding documents: before 09:00 am, 10 December 2020 (during office hours)

Bid opening time: before 09:00 am, 10 December 2020