Procuring agency: Viet Nam Paper Corporation
Name of procurement package: Package No.2 – Investigation, Engineering, Procurement and Related Technical Services “Notice ref No.: 20190462660 - 00. Date of publication: 24/04/2019 10:53"
- Implementation period: 240 days
Project name: The new investment project of Electrostatic Precipitator System (ESP) for heat recovery boilers at the Power Plant.
Source of fund: Equity capital and Commecial capital
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 02:00 pm, 02 May 2019 to 09:30 pm, 12 June 2019 (during office hours)
Place of issuing bidding documents: The Construction Department, Viet Nam Paper Corporation, 12 Floor, Hong Ha Center building, 25 Ly Thuong Kiet, Hoan Kiem, Ha Noi city
Price of bidding documents:VND 2,000,000
Bid security: VND 650,000,000 or USD 250 by bank guarantee or deposit by certified cheque
Bid closing time: 09:30 pm, 12 June 2019