The Northern VietNam Power Projects Management Board: Supply and Delivery of Primary Equipment and Materials

The Northern VietNam Power Projects Management Board issued on March 22, 2019 its notice of bid invitation for procurement package: Package 02: Supply and Delivery of Primary Equipment and Materials with details as follows:

Procuring agency: The Northern VietNam Power Projects Management Board

Name of procurement package: Package 02: Supply and Delivery of Primary Equipment and Materials “Notice ref No.: 20190354170 - 00. Date of publication: 22/03/2019 08:58"

- Implementation period: 180 days

Project name: Installation of 220kV Auto-transformer at 220kV Than Uyen Substation.

Source of fund: The National Power Transmission Corporation

Method of bidder selection: International open bidding, one-stage two envelope bidding  

Time of issuing bidding documents: from 08:00 am, 29 March 2019 to 09:00 am, 08 May 2019 (during office hours)

Place of issuing bidding documents: The Northern VietNam Power Projects Management Board No.4 Nguyen Khac Nhu street, Ba Dinh district, Ha Noi, Viet Nam. Tel: +84-24-22103081/39840823; Fax: +84 -24-39840824

Price of bidding documents:VND 4,000,000 or USD 200

Bid security: VND 219,409,000 or USD 9,000 by bank guarantee or deposit by certified cheque

Bid closing time: 09:00 am, 08 May 2019 

Bid opening time: 09:30 am, 08 May 2019