CPMB issued on August 19, 2021 its notice of its notice of bid invitation for procurement package of Supply and transportation of 500kV-900MVA auto-transformer with details as follows:

Procuring agency: Central Power Projects Management Board (CPMB)

Name of procurement package: Package No. 11: Supply and transportation of 500kV-900MVA auto-transformer “Notice ref No 20210851150 - 00. Date of publication: 19/08/2021 16:57"

- Implementation period: 270 days

Project name: 500kV Van Phong substation and connection line

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 04:57 pm, 19 August 2021 to 09:00 am, 04 October 2021 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 7,000,000 or USD 300

Bid security: VND 8,100,000,000 or USD 350,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 04 October 2021

Bid opening time: 09:00 am, 04 October 2021.