The Southern Vietnam Power Projects Management Board (SPMB): Supply of primary equipment and materials for substation (including inspection and sample approval)

The Southern Vietnam Power Projects Management Board (SPMB) issued on March 29, 2019 its notice of bid invitation for procurement package: Package 5: “Supply of primary equipment and materials for substation (including inspection and sample approval), conductors, earthwires, insulators & fittings, OPGW and fittings for transmission line” with details as follows:

Procuring agency: The Southern Vietnam Power Projects Management Board (SPMB)

Name of procurement package: Package 5: “Supply of primary equipment and materials for substation (including inspection and sample approval), conductors, earthwires, insulators & fittings, OPGW and fittings for transmission line” “Notice ref No.: 20190373322 - 00. Date of publication: 29/03/2019 09:11"

- Implementation period: 05 months

Project name: 220kV Ben Luc Substation.

Source of fund: National Power Transmission Corporation (EVNNPT)

Method of bidder selection: International open bidding, one-stage two envelope bidding  

Time of issuing bidding documents: from 08:00 am, 04 April 2019 to 09:00 am, 20 May 2019 (during office hours)

Place of issuing bidding documents: Southern Vietnam Power Projects Management Board No. 610 Vo Van Kiet Street, Cau Kho Ward, District 1, Ho Chi Minh City, Vietnam. Tel: (84-28) 2210 0719; Fax: (84-28) 3836 1096

Price of bidding documents:VND 4,600,000 or USD 200

Bid security: VND 1,026,000,000 or USD 44,130 by bank guarantee or deposit by certified cheque

Bid closing time: 09:00 am, 20 May 2019 

Bid opening time: 09:15 am, 20 May 2019.